Rough estimate of the building

ESTIMATE of the two-storey building: 61,133 GHC / 9.830 Euro / 10.673 USD

For now we want to start with the construction of two floors.

If the Foundation can expand even further in the future with a professional training, then this is possible!

Blocks: 6 inches solid = 2667 bricks /  986 GHC / 180 Euro/ 225 USD _ 6 inches hollow= 1667 bricks/ 500 GHC/ 93 Euro / 115 USD

Sand: 2,5 Trips  = GHC 1867 /340 euro/420 USD

Stone: 2,5 Trips = GHC 4267 / 780 Euro / 1000 USD

Cement:400 Bags = GHC 12000 / 2.200 euro/2735USD

Iron Rodd: 5/8mm 4,5 tons GHC 2858 / 520 Euro / 640 USD _12mm  4 tons GHC 2480 / 454 Euro / 567 USD_3/8mm 2 tons GHC 1240 / 226 Euro /285 USD_Binding Wire 2 bundles  GHC 46 / 8,5 Euro / 10,5 USD

Electricals: GHC 3596 / 667 Euro/800 USD

Plumbing: GHC 9667 / 1800 Euro /2200 USD

Roofing: GHC 12800 / 2334 Euro /2933 USD

Carpentry: GHC 10000 / 1867 Euro / 2267 US

====================

 Hereby the total Estimate of the building included tiles, paint, furniture etc       

Total Estmate Uhuru Training Centre_ two floors_E_M